Tech Services Commitee Sept 07

Killarney Water Treatment Plant Sludge Beds

Draft design plans have been completed for construction of sludge beds and improvements to the access road.

North Killarney Drainage

Design proposals have been received from Consultants and are currently being reviewed.

Negotiations have commenced with affected landowners for possible land acquisition for drainage requirements.

Bridge Replacement Brosnans Bridge

Northern and southern abutments have been constructed. Deck units were installed 12 September. Expected completion date end of September.


 
 