Tech Services Commitee Sept 07 |
|
Killarney Water Treatment Plant Sludge Beds Draft design plans have been completed for construction of sludge beds and improvements to the access road. North Killarney Drainage Design proposals have been received from Consultants and are currently being reviewed. Negotiations have commenced with affected landowners for possible land acquisition for drainage requirements. Bridge Replacement Brosnans Bridge Northern and southern abutments have been constructed. Deck units were installed 12 September. Expected completion date end of September.
|